ArcelorMittal Poland to review the economic viability of the reline of blast furnace no. 2 in Dabrowa Gornicza

ArcelorMittal Poland informs that the company has decided to review the economic viability of the reline of blast furnace no. 2 in its Dabrowa Gornicza Unit. The decision stems from the uncertainty caused by EU ETS system for NAP4, which is to be agreed mid-2017.

The blast furnace no. 2 at former Huta Katowice, currently Dabrowa Gornicza Unit of ArcelorMittal Poland, is due for an end of life repair in the second half of 2018. This means that the preparatory works for this project should start now as to allow for detailed engineering and ordering of all required components. The company, however, has decided to review the economic viability of this undertaking in view of the uncertainty of NAP4 (national allocation plan for carbon dioxide emissions, which will be in force between 2021 and 2030) under the EU ETS (Emissions Trading System), which is to be decided in mid-2017.

The current ETS proposal of the Commission will jeopardise the competitiveness of not only steel-making in Poland, but the steel industry in Europe more broadly. Due to the unrealistic benchmark set for the sector, which is technically unachievable even for the most efficient steel plants, the shortage of carbon credits will be significant. The steel industry is the only industry for which the benchmark set does not actually reflect the best-performing plant today. Additionally, the forecast price of emission rights for a tonne of CO2 may reach as much as EUR 30. This will translate onto significantly higher production costs since on the average two tonnes of CO2 are emitted per tonne of liquid steel.

 Sanjay Samaddar, Chairman of the Board of ArcelorMittal Poland, said “Since ArcelorMittal came to Poland in 2003 we have invested in excess of PLN 6 bn in the Polish steel industry. We have transformed the business, improved its productivity and competitiveness, expanded its product base and established a high quality operation in a region of the world with good long-term steel demand growth prospects. Following the re-line of the blast furnace in Cracow in 2016, blast furnace number 2 in Dabrowa Gornicza will require an end of life repair during 2018. However, with the uncertainty caused by the next iteration of the ETS which will bring considerable additional cost post 2020, it is not clear at this stage whether such a significant investment can be justified economically”.

 The huge modernization expenditure of ArcelorMittal Poland and the transformation of the Polish steel industry could be in vain if European steel producers have to pay an additional cost that other steel companies, producing elsewhere, but selling into Europe, do not have to pay. It would be a great shame if Poland’s steel demand cannot be met by its own steel capacity, but the new ETS terms will give a competitive advantage to steel companies operating outside Europe which, in an environment of overcapacity and low margins, is likely to render parts of the European steel industry uncompetitive, including here in Poland.

  “If the new EU ETS proposal is accepted in its current form, which we truly hope will not finally be the case, the initial calculations that we have carried out show that a two-furnace operation in Dabrowa Gornicza may not be economically viable. We understand the importance of transitioning to a low carbon economy and we want to contribute – however, any legislation should take into account the realities of global steel industry trade and not hand an unfair competitive advantage to competitors from overseas. We hope that ultimately the final legislation will be amended to better protect European industry, but until there is certainty on that we must be prudent and review the planned reline investment of blast furnace no. 2, as well as other investment projects in the unit and at the plant in Zdzieszowice, which supplies coke to Dabrowa Gornicza. As part of this review we will carry out detailed studies to fully analyse the profitability and sustainability of potential footprint scenarios of our plants in Dabrowa Gornicza and Zdzieszowice in the NAP4 period”, added Sanjay Samaddar.

Blast furnace is a piece of equipment, in which hot metal is made from iron ore with the use of coke as fuel. Hot metal and scrap are then used at the steel shop to make steel. Blast furnaces need to be relined periodically due to their normal wear and tear. The cost of relines is significant, and hence such decisions need to be economically viable and sustainable during the lifetime of the repaired furnace.

Since completion of the privatization process of Polskie Huty Stali in 2004, ArcelorMittal Poland has invested in its operations over PLN 6 bn, modernizing practically each stage of steel-making, both in the liquid and processing phase. As a result of this, the company’s plants are well positioned to cater to the growing steel demand in Poland. Krakow is now home to Europe’s most modern hot strip mill and Dabrowa Gornicza is one of only a few steel plants worldwide able to produce 120-m long rail. Only recently the company has completed an investment programme at its Krakow unit. The value of projects, including the re-line of the only blast furnace, has exceeded PLN 500 m. ArcelorMittal Poland’s investments have also translated onto reduction of its environmental footprint – dust emissions have gone down by 30 per cent and CO2 emissions by 25 per cent. The company’s focus now are investments aimed at adjusting its installations to the stringent requirements of the EU’s Industrial Emissions Directive, which come into force in 2018. The estimated value of these projects is in the region of PLN 1 bn. Some of them have already been completed, such as modernization of the dedusting system of the blast furnace in Krakow and the by-products department in Zdzieszowice.

 

 

Back button-arrow

Information on the use of cookies by the ArcelorMittal Poland website:

The poland.arcelormittal.com website uses technology that stores and accesses information on the user's end device (in particular, using cookies). Consent expressed to the use of these technologies by poland.arcelormittal.com or third parties for purposes related to the provision of electronic services may be modified or revoked at any time in the browser settings.

More information can be found in the "Privacy Policy of the poland.arcelormittal.com website"